Publications
No Extension of Arbitration Agreement to Subcontractor
Simon Gabriel;
in: dRSK, 07.01.2021
Commentary on Swiss Federal Tribunal decision 4A_124/2020 on November 13, 2020
The Swiss Federal Tribunal set aside an interim award which extended the arbitration agreement of a main contract to a subcontractor for reasons of its interference in the conclusion and performance of the main contract: The officially communicated position of the subcontractor supersedes actions which might otherwise be sufficient for an extension of an arbitration agreement to a non-signatory.
I. Background
[1] In ICC arbitration proceedings with seat in Geneva, Switzerland the contractor («Contractor») of a power plant in Bangladesh sued its customers («Customers») for payment of open invoices under the main contract («Main Contract»; sec. A.a, A.b, and B).
[2] In these arbitration proceedings, the Customers submitted counterclaims and a request for a third party joinder of the Contractor’s subcontractor who had delivered the relevant engines for the power plant («Subcontractor») under a separate supply contract with the Contractor («Subcontract»; sec. A.b and B).
[3] The Subcontractor was not a signatory to the Main Contract which included the relevant arbitration agreement. But it contributed to the Main Contract regarding the engines in various ways (sec. A.c).
[4] It should also be noted that the Contractor and the Subcontractor were at least at some point in time affiliated, but at all times clearly distinguishable so that there was no argument of an undue mixing of spheres of companies of the same group (sec. 3.2).
[5] Nevertheless, the arbitral tribunal identified six indications in particular which, in the arbitral tribunal’s view, were sufficient to extend the arbitration agreement of the Main Contract to the Subcontractor (sec. 3.2):
- The Subcontractor was present at the first meeting between the Contractor and the Customers.
- The Subcontractor delivered an appendix to the Main Contract regarding the specifications of the engines and the test procedures.
- During the installation of the power plant, the Subcontractor installed and modified the engines on site.
- The Subcontractor directly communicated with the Customers with respect to defects of the engines.
- In an e‑mail (Exhibit R‑22), the Contractor, apparently after discussions with the Subcontractor, confirmed that the Contractor would guarantee the quality of the engines together with the Subcontractor.
- In a letter which was sent in the name of the Contractor and the Subcontractor by a person that was apparently an authorized representative of both companies at that time (Exhibit R‑25), both companies in essence promised to do whatever was necessary to remedy any defects of the engines.
[6] Based on these indications, the arbitral tribunal decided in an interim award that it had jurisdiction over the Subcontractor as a result of the Subcontractor’s interference in the Main Contract (sec. 3.2).
[7] The Subcontractor initiated setting aside proceedings against the interim award of the arbitral tribunal before the Swiss Federal Tribunal and challenged the decision on jurisdiction.
II. Decision
[8] The Swiss Federal Tribunal first refers to its longstanding jurisprudence regarding the interpretation of arbitration agreements and extension to non-signatories (sec. 3.1). It emphasizes in this regard that the extension of an arbitration agreement to a non-signatory is indeed possible under certain conditions, but a restrictive interpretation standard applies when the exclusion of the ordinary state court jurisdiction is at issue (sec. 3.1.2).
[9] The Federal Tribunal further notes that the arbitral tribunal did not find an actual consent of the Customers and the Subcontractor to arbitrate, but rather decided to extend the arbitration agreement of the Main Agreement as a result of the interpretation of the behaviour of the Subcontractor. Therefore, the question at issue is a legal question which the Swiss Federal Tribunal reviews with full degree of scrutiny. In contrast, the (factual) finding of an actual consent to arbitrate by an arbitral tribunal would be binding for the Federal Tribunal and could not be reviewed from a factual point of view (sec. 3.3).
[10] When analysing the individual indications mentioned in the interim award, the Swiss Federal Tribunal emphasizes that the Subcontractor was expressly mentioned as subcontractor for the engines of the relevant power plant in the Main Agreement itself (in Annex 1 thereto). It could thus not be surprising that the Subcontractor in its function as sub-supplier of engines, also contributed to the specifications of these engines in the Main Contract and attended meetings with the Customers (sec. 3.3.2).
[11] The Customers must thus have been aware that any contributions of the Subcontractor to the Main Agreement were precisely made in its function of a subcontractor. These contributions could thus not have been reasonably (mis)understood as interference in the Main Contract in the sense of an implicit acceptance of the Subcontractor to be a party thereto (sec. 3.3.2).
[12] The Federal Tribunal also underlines that the evident contractual function of the Subcontractor constitutes an important difference compared to BGE 129 III 727 where an individual interfered in a contractual performance without having a contractually agreed function in the relevant project (sec. 3.3.2).
[13] The Federal Tribunal finally also analyses the Exhibits R‑22 and R‑25 and concludes that the statements made therein were not sufficient expressions of the Subcontractor to agree to arbitration in light of the restrictive interpretation standard and the general context of the case (sec. 3.3.2).
[14] For these reasons the Federal Tribunal set aside the decision of the arbitral tribunal and referred the case back for a new decision.
III. Comments
[15] First, the present decision concerns the extension of an arbitration agreement to a non-signatory with a special status in a project: namely, the subcontractor of one of the parties to the relevant arbitration agreement.
[16] The core statement of the decision is: The officially communicated position of a party in a project as subcontractor supersedes actions of this party which might – otherwise – be seen as sufficient for an extension of an arbitration agreement to a non-signatory.
[17] Specifically, if a party is referred to in a contract itself as subcontractor to the main contractor, there is an assumption that this party will act in the function of a subcontractor when it contributes to a project (rather than de facto accepting the position of another contractor under the main contract).
[18] In the author’s view, the present decision reflects a reasonable approach which provides legal certainty for projects with numerous parties working in different functions.
[19] This clarification is also welcome in view of expected COVID-19 cases where typically several contractors and subcontractors or suppliers and sub-suppliers in supply chains could be considered as jointly responsible for delays or disruptions in projects.
[20] To the extent that these subcontractors’ respective positions have been transparently communicated in a project, it will be very difficult to drag them into arbitration proceedings under an arbitration agreement which they have not signed.
[21] Second, the present decision illustrates how delicate and still how important the legal distinction between (i) an actual consent to an arbitration agreement (i.e. a factual finding) and (ii) the interpretation of an arbitration agreement or the behaviour of a party (i.e. a legal interpretation) can be: Only the second conclusion (interpretation) can be reviewed by the Federal Tribunal in setting aside proceedings
[22] Had the arbitral tribunal found (after hearing witnesses) that e.g. Exhibit R‑25 reflected the actual intention of the Subcontractor to jointly assume certain obligations under the Main Contract together with the Contractor and thus also to accept the arbitration agreement in the Main Contract, this finding could not have been reviewed and overturned by the Federal Tribunal.
[23] Consequently, it is of crucial importance for arbitral tribunals to clearly distinguish between the factual finding of an actual consent of parties to arbitrate and the legal interpretation of an arbitration agreement or the behaviour of a party in this regard.